Changes in regulatory rulings

Regulatory update - Texas
ERCOT Regulatory Highlights: February 2017
ERCOT Regulatory Highlights: February 2017

This month…

  • An NPRR was introduced to change the load participation limitations for Responsive Reserve Service.
  • The Emergency Response Service (ERS) proposed rule for adoption was filed by PUC staff. 
  • The Reliability Must Run (RMR) rulemaking continues, a workshop was held in December.
  • The testimony and reply testimony for the acquisition of Oncor by NextEra has been filed.
  • The Texas Legislature convened January 10, 2017.
  • Texas PUC Issues Final Report On Alternative Ratemaking.

Feb 09, 2017
Regulatory update - Texas
ERCOT Regulatory Highlights: January 2017
ERCOT Regulatory Highlights: January 2017

This month…

  • ERCOT Released its December Capacity, Demand, and Reserves Report.
  • The ERCOT Board approved the 2017 Ancillary Service Methodology.
  • The Emergency Response Service (ERS) proposed rule was published and comments and reply comments have been filed.
  • The Reliability Must Run (RMR) rulemaking continues, a workshop was held in December.
  • The PUC approved Distributed Generation Interconnection rules.
  • The PUC set a schedule for the review of the acquisition of Oncor by NextEra.
  • The Texas Legislature convenes January 10, 2017.

Jan 06, 2017
Regulatory update - Texas
ERCOT Regulatory Highlights: December 2016
ERCOT Regulatory Highlights: December 2016

This month…

  • ERCOT is moving forward with different Reserve Margin Target options.
  • The Emergency Response Service (ERS) proposed rule comments were filed in November, reply comments were filed in early in December.
  • The Reliability Must Run (RMR) rulemaking continues, a workshop is scheduled for December.
  • The PUC continues to discuss Distributed Generation Interconnection rules.
  • The PUC set a schedule for the review of the acquisition of Oncor by NextEra.

Dec 08, 2016
Regulatory update - Texas
ERCOT Regulatory Highlights: November 2016
ERCOT Regulatory Highlights: November 2016

This month…

  • Reserve Margin Target options are back up for discussion at the PUC.
  • ERCOT Releases Winter Seasonal Assessment of Resource Adequacy.
  • Commissioners approved a proposed rule for publication for Emergency Response Service (ERS) changes with comments due in December.
  • Numerous Reliability Must Run (RMR) items changed this month, including Board approval of new procedures and reconsideration of the NRG and Calpine RMR determinations.

Nov 17, 2016
Regulatory update - Texas
ERCOT Regulatory Highlights: October 2016
ERCOT Regulatory Highlights: October 2016

This month…

  • Reserve Margin Target options are back up for discussion at the PUC.
  • Stakeholders filed comments regarding changing the Emergency Response Service (ERS) program and Commissioners provided guidance for how to move ahead.
  • Numerous Reliability Must Run (RMR) items were discussed this month, including TAC approval of new procedures.
  • Calpine filed a Notice of Suspension of Operations for resources in the Houston Load Zone and in an initial determination, ERCOT indicates the units are needed for reliability.

Oct 10, 2016
Regulatory update - Texas
ERCOT Regulatory Highlights: September 2016
ERCOT Regulatory Highlights: September 2016

This month…

  • Reserve Margin Target discussions and other market design issues remain on hold at the PUC.
  • ERCOT filed the Seasonal Assessment of Resource Adequacy for Fall
  • Numerous stakeholders filed comments regarding changing the Emergency Response Service (ERS) program and PUC staff seeks further direction from Commissioners.
  • NRG’s Greens Bayou Unit 5 (GB5) is now under Reliability Must Run contract with ERCOT.  ERCOT issued an RFP for Must Run Alternatives (MRA) to GB5 in July.  Final MRA decisions will be made this month.
  • Calpine filed a Notice of Suspension of Operations for resources in the Houston Load Zone and in an initial determination, ERCOT indicates the units are needed for reliability.
  • The PUC is investigating Alternative Ratemaking Mechanisms.
  • The PUC Approved a Proposal for Publication Related to Distributed Generation Interconnection Agreement.

Sep 06, 2016
Regulatory update - Texas
ERCOT Regulatory Highlights: August 2016
ERCOT Regulatory Highlights: August 2016

This month…

  • The PUC received more comments on the planning reserve margin target.
  • Numerous stakeholders filed comments regarding changing the Emergency Response Service (ERS) program.
  • NRG’s Greens Bayou Unit 5 (GB5) is now under Reliability Must Run contract with ERCOT.  ERCOT issued an RFP for Must Run Alternatives to GB5 in July.  Proposals are due in August.
  • ERCOT EMS Failure results in need for resettlement of July 7.
  • The PUC hired a consultant to report on Alternative Ratemaking Mechanisms, the report has been released.
  • The PUC Approved a Proposal for Publication Related to Distributed Generation Interconnection Agreements.

Aug 09, 2016
Regulatory update - Texas
ERCOT Regulatory Highlights: July 2016
ERCOT Regulatory Highlights: July 2016

This month…

  • Modifications to the 2016 Ancillary Services Methodology go into effect July 1.
  • The Independent Market Monitor filed the State of the Market Report for ERCOT.
  • The PUC requested comments regarding changing the Emergency Response Service (ERS) program.
  • NRG’s Greens Bayou Unit 5 (GB5) is now under Reliability Must Run contract with ERCOT.  ERCOT will issue an RFP for Must Run Alternatives to GB5 in July.
  • The Future Ancillary Services Overhaul rejection was not appealed to the Board.

Jul 06, 2016
Regulatory update - Texas
ERCOT Regulatory Highlights: June 2016
ERCOT Regulatory Highlights: June 2016

This month…

  • Modifications to the 2016 Ancillary Services Methodology have been introduced and approved at the TAC level.
  • After conditional approval by the PUC of the transfer of ownership of Oncor to Hunt, Hunt filed for a motion for rehearing, then asked the PUC to vacate the final order without prejudice.
  • The PUC opened a rulemaking to investigate changing the Emergency Response Service (ERS) program.
  • NRG’s Greens Bayou Unit 5 is now under Reliability Must Run contract with ERCOT.
  • ERCOT stakeholders rejected the Future Ancillary Services Overhaul.

Jun 08, 2016
Regulatory update - Texas
ERCOT Regulatory Highlights: May 2016
ERCOT Regulatory Highlights: May 2016

This month…

  • The Public Utility Commission (PUC) received comments on Project No. 45572 which was opened to review the parameters of the Operating Reserve Demand Curve (ORDC).
  • ERCOT released the May Capacity, Demand, and Reserves Report and the Summer Seasonal Assessment of Resource Adequacy.
  • Several proposals for modifications to the 2016 Ancillary Services Methodology have been introduced and approved.
  • After conditional approval by the PUC of the transfer of ownership of Oncor to Hunt, Hunt filed for a motion for rehearing.
  • PUC to open rulemaking and investigate changing the Emergency Response Service (ERS) program.
  • ERCOT continues work on the future Ancillary Services Overhaul

May 09, 2016

Archive

Set your ZIP code and utility

Enter a valid ZIP code
Unfortunately, we don't currently service this area. Please try another ZIP code.

Loading please wait...

Don't see your utility?

We currently only provide service to the listed utilities. For question, please contact 1-888-925-9115.

Loading...

54.163.65.30